What is a typical contractor payment schedule in California?
A safe payment schedule ties draws to completed milestones — never to the calendar. A common pattern: 10% deposit (or $1k cap), 20% at rough framing/demo complete, 25% at rough mechanicals, 25% at drywall, 15% at substantial completion, 5% retention released after final punch list and lien waivers.